A Production Plan helps in production and material planning for the Items planned for manufacturing. These production items can be committed via Sales Order (to Customers) or Material Requests (internally).
Production Plan helps the user to plan production against multiple Sales Orders or the Material Requests. Also, it helps in Material Procurement planning for the raw material item, based on the quantity of finished products to be manufactured.
To access the Production Plan list, go to:
Home > Manufacturing > Production > Production Plan
Before creating and using a Production Plan, it is advised that you create the following first:
As mentioned earlier, a Production Plan can be used for planning the manufacture of Items against Sales Orders or Material Requests.
The common steps are:
A Production Plan can also be created manually where you can select the Items to manufacture.
2. Click on Get Sales Orders to fetch sales orders based on the above filters.
3. Click on 'Get Items for Work Order' to fetch the items from the above Sales Orders. Items only for which a BOM is present will be fetched. 4. On expanding a row in the Items to Manufacture table, you'll see an option to 'Include Exploded Items'. Ticking this includes raw materials of the sub-assembly items in the production process. 5. If "Consolidate Items" is ticked and saved, items with the same BOM are combined into a single item with the combined total planned quantity.
2. Click on 'Get Material Request' to fetch material requests based on the above filters.
3. Click on Get Items for Work Order to fetch the items from the above material requests.
Clicking on the 'Get Raw Materials for Production' button will fetch the required raw material Items in the Material Request Plan table. For example, to manufacture 200 plastic canes, you need 100 raw plastic Nos but have only 20 in your Warehouse, then clicking this button will add a row with 80 in the Required Quantity column.
Use the following checkboxes to perform certain actions:
Once the Production Plan is submitted, the User gets an option to make Work Orders for the production items and Material Requests for the raw materials. Users can also set the Status as Closed in the Production Plan.
There could be occurrences where a Production Plan is partially complete and is going to be discontinued. This could happen due to reasons such as:
In cases like these, Users can set the Production Plan status to Closed, so that no new Work Orders or Material Requests are created against it.
The same can be Re-opened.
In the above screenshot, the User creates the Shaving Brush Bristles first and then creates final finished goods.
Here, the User wants to make the work order for Shaving Brush Bristles, to do this, the user has to enable the field "Make Work Order for Sub Assembly Items" in the Production Plan against the item Shaving Brush.
On clicking make Work Order, the system will generate the Work Order for the sub-assembly items and the finished good items: